State Road 542 Design Projects
Project Schedules (Dates are tentative and subject to change.)
Project 1
Financial Project ID: 410666-2-52-01
Federal ID: 2241 006 P
Design of SR 542 from 1st Street to east of Buckeye Loop Road
Length: 2.4 miles
Plans Production
Phase I | December 2011 - Complete | |
Phase II | December 2012 - Complete | |
Determine Final ROW Requirements | March 2014 - Complete | |
Phase III | June 2014 - Complete | |
Phase IV | November 2017 - Complete | |
ROW Acquisition Phase | Fiscal Years 2014/2015 through 2016/2017 - Complete | |
Construction | Letting June 14, 2018 Begin Construction Fall 2018 |
Lanscape Only Project
Financial Project ID: 410666-4-52-01
Phase II | Summer 2018 | |
Phase III | Winter 2018 | |
Pahe IV | Summer 2019 | |
Construction | Fiscal Year 2021/2022 |
Project 2
Financial Project ID: 410666-3-32-01
Federal ID: 2241 007 P
Design of SR 542 from east of Buckeye Loop Road to US 27
Length: 3.9 miles
Plans Production
Phase I | January 2012 - Complete | |
Phase II | November 2014 - Complete | |
Determine Final ROW Requirements | July 2015 - Complete | |
Phase III | Fall 2016 | |
Phase IV | Fall 2018 | |
ROW Acquisition Phase | Fiscal Years 2015/2016 through 2018/2019 | |
Construction | Fiscal Years 2019/2020 |